i have not done this reciently, but i have in the past backfeed a perminant electrical panel from a temporary panel.
The situation is this: We have a temporary meter/panel installed for construction. The perminant panel is installed. Several areas of the building have lighting circuits that are complete. The rooms are ready for painting and the painter needs the perminant lights turned on to be able to see what he is doing better.
I ran one #12-3 circuit from the temporary pole to the perminant panel. Connected the neutral wire to the neutral/ground bar at both ends.
put the two hot conductors on breakers at the temp pole, and wirenuted the circits needed from the temp wire to the branch circuit wires that i wanted to have energized.
Is this safe?
The situation is this: We have a temporary meter/panel installed for construction. The perminant panel is installed. Several areas of the building have lighting circuits that are complete. The rooms are ready for painting and the painter needs the perminant lights turned on to be able to see what he is doing better.
I ran one #12-3 circuit from the temporary pole to the perminant panel. Connected the neutral wire to the neutral/ground bar at both ends.
put the two hot conductors on breakers at the temp pole, and wirenuted the circits needed from the temp wire to the branch circuit wires that i wanted to have energized.
Is this safe?