hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
I have bakery factory and has kitchen. The kitchen has two 200 quart mixers 208V, 3 phase, 7 HP each. The panelboard feeding these mixers is in separate warehouse room and drawings show conduit from panelboard go underneath slab come up into junction box next to mixers.
I was wondering if the mixers would require disconnects per code 2014 or can it be straight hardwire without disconnect at the mixers?
I was wondering if the mixers would require disconnects per code 2014 or can it be straight hardwire without disconnect at the mixers?