Hi,
We're looking at getting primary metered at a new project in New York. I am trying to determine the ballpark added cost for the extra equipment. I have the transformer cost but RSMeans doesn't have much information for 13.2kV gear. For our 3 phase feed we'll need:
load break switch with operating shaft & handle
lightning arrestor
fused cutouts
3 CTs, 3 PTs
and a couple poles for the overhead feed.
Anyone have numbers (including labor) to throw at this type of install?
We're looking at getting primary metered at a new project in New York. I am trying to determine the ballpark added cost for the extra equipment. I have the transformer cost but RSMeans doesn't have much information for 13.2kV gear. For our 3 phase feed we'll need:
load break switch with operating shaft & handle
lightning arrestor
fused cutouts
3 CTs, 3 PTs
and a couple poles for the overhead feed.
Anyone have numbers (including labor) to throw at this type of install?