Doing a TI that already has an existing generator. One of the panels I need to Demo feeds the battery charger on the backup generator.
I will be moving this charger circuit to temp power.
Question is will I need to have the generator commissioned when I put this on temp power?
I’m thinking no because I will be having a start up test on the generator with the manufacturer when I am 100% done with the project.
Any thoughts??
I will be moving this charger circuit to temp power.
Question is will I need to have the generator commissioned when I put this on temp power?
I’m thinking no because I will be having a start up test on the generator with the manufacturer when I am 100% done with the project.