I have an inspector telling me that I either need to provide load calcs or upsize the current 4/0 AL service wire, since we added the solar supply side connection, He said since we are tapping the derate does not apply to the wire anymore. I don't believe this is needed since we are not a tap, since we are supply side. Am I missing something?