It's after 5 so i can't call the supply house to see what kind of products are carried. If it were a residential application, I'd just get a 320 class meter and double tap each phase for each panel. However, we are talking about a commercial site, and the owner wants a 400A service. The panels are going on an exterior wall, and the meter will be right behind them outside. Do the same principles apply? Does a 3 phase meter base that can be double tapped exist? I've been looking all over the net to no avail. If not I'm planning to get a 400A meter base with (2) 200A breakers in it. As long as there 400 amps of power, the owner doesn't care how many electrical panels there are. I don't think a 400A single panel, if it exists, would be cost efficient. I'm looking for a small amount of guidance here. I'll be calling the supply house when it opens, just trying to get ahead of this thing a little.