Open Neutral
Senior Member
- Location
- Inside the Beltway
- Occupation
- Engineer
In a forum about transit, the question of spacing of the Traction Power Stations came up. On WMATA, the newly upgraded (from 6MW) stations are 9MW, are fed from a dedicated 13.2KV (MD) or ~34KV [VA] PoCo feeder, and deliver 750 VDC. They are about a mile apart.
I started pondering the conductor size for such. (It got into the thread because at one point, the trackage is 200+ feet below the TPS.) Assuming 100% both of the accuracy of the term, and efficiency, that's 12E3 amps. My copper wire table does not seem to include that current.
My visual memory is about six cables bolted to the third rail, or the Wee-Z bond. They appeared to be roughly four aught size, but would seem to need to be far larger.
Anyone here with experience with the DC plant of such and able to comment?
(A Wee-Z bond is a inductor to pass the DC traction power from the rails back to the TDS, but block the audio frequencies used for signaling. The bond also seeks to balance the current through the two rails.)
I started pondering the conductor size for such. (It got into the thread because at one point, the trackage is 200+ feet below the TPS.) Assuming 100% both of the accuracy of the term, and efficiency, that's 12E3 amps. My copper wire table does not seem to include that current.
My visual memory is about six cables bolted to the third rail, or the Wee-Z bond. They appeared to be roughly four aught size, but would seem to need to be far larger.
Anyone here with experience with the DC plant of such and able to comment?
(A Wee-Z bond is a inductor to pass the DC traction power from the rails back to the TDS, but block the audio frequencies used for signaling. The bond also seeks to balance the current through the two rails.)