J.P.
Senior Member
- Location
- United States
At high school gym two new A/C, heat units went in for the gymnasium. They ran a whole separate plastic underground line and meter for the units.
The pipe runs along the wall doesn't get close to our electrical pipe and goes into the units we are supplying power to.
Should I bond the gas pipe? It never penetrates the wall. It doesn't cross our elec pipe.
If I do bond it....is the wire sized off the service entrance conductors for the main service ( 500A parallel 250s)? Or will the # 6 equip ground that is in the A/C disconnect ( 125A #1 ) suffice?
It may be a clear cut issue for some of you, but for me I could go three ways........
The pipe runs along the wall doesn't get close to our electrical pipe and goes into the units we are supplying power to.
Should I bond the gas pipe? It never penetrates the wall. It doesn't cross our elec pipe.
If I do bond it....is the wire sized off the service entrance conductors for the main service ( 500A parallel 250s)? Or will the # 6 equip ground that is in the A/C disconnect ( 125A #1 ) suffice?
It may be a clear cut issue for some of you, but for me I could go three ways........
Last edited: