Shawn pavich
Member
- Location
- Fresno ca
Hi everyone this is my first post. I have used mike holts fourm many times but never posted,So here I go.we have a existing 200 amp surface mount MSP over head 2" IMC 4/0 AL,2" conduit goes threw top plate down wall goes into a LB then goes into MSP threw back with a chase nipple .the plans call for a 400 amp MSP over head BTW this is a residential and solar project 80 amp back feed PG&E said we can use existing over head 2"conduit and 4/0 for the new 400 MSP which I know to be wrong but if that's what they approve then who I'm I to disagree my ? Is from what I know that a chase nipple going into a conduit body is not a a proper bonding I'm thinking of putting a bonding wedge between the flat side of chase nipple and MSP thank for your back feed in advance