I have two 4" EMT conduits that feed a cable tray for Data/communications circuits in an office. What does the NEC require for bonding of the tray to the 4" conduits providing a pathway from the MDF to the tray?
 
So far the closest thing I can find is in 392.60 where ti discusses bonding cable tray containing non-powered conductors and bonding jumpers at transitions.
 