Had a rough in inspection on a pipe run of (4)- 3 inch conduits going thru two 24x36 pullboxes. All fittings were compression on a indoor installation.
In the pull boxes we used 3 inch grounding bushings with lugs on top of the locknuts and tied everything together with #4 solid copper. #4 went thru each lug from one side of box to the other stopping in between to attach to a lug on the box. One continuous piece of copper. Inspector said it was not correct, didn't like it and wouldn't say what should be changed.
Blueprint called for grounding bushings and #4. Didn't specify stranded or solid. Our intent was to provide complete bonding of all pieces together.
This is a sub-feed run, not a service entrance.
Normally in the bottom of service gear one piece of number 6 is used to loop all conduits and then tie to the ground bar but this isn't service entrance.
Any thoughts?
In the pull boxes we used 3 inch grounding bushings with lugs on top of the locknuts and tied everything together with #4 solid copper. #4 went thru each lug from one side of box to the other stopping in between to attach to a lug on the box. One continuous piece of copper. Inspector said it was not correct, didn't like it and wouldn't say what should be changed.
Blueprint called for grounding bushings and #4. Didn't specify stranded or solid. Our intent was to provide complete bonding of all pieces together.
This is a sub-feed run, not a service entrance.
Normally in the bottom of service gear one piece of number 6 is used to loop all conduits and then tie to the ground bar but this isn't service entrance.
Any thoughts?