We have a 2500Kva Padmount Transformer. Primary 12,470, with a 480/277v secondary. The "service entrance" conductors consisted of 8 paralleled 500MCM copper conductors with a full size neutral going to a 3000Amp Main Breaker, with a "number" of "fusible" branch feeders. We established the "bond" in the switchboard at the neutral bar, by running a seperate 3/0 copper to EACH of the following points. 1. Incoming water pipe. 2. To the Building Steel. 3. Rebar steel in the footer of the building.
My question is this: In the 2500kva transformer "hanging" from the Neutral Bushing is a "strap" with a hole in the end of the strap. Since we are "bonded" in the SWBD at the Neutral don't we let this strap in the transformer stay in the "disconnected" position?
My question is this: In the 2500kva transformer "hanging" from the Neutral Bushing is a "strap" with a hole in the end of the strap. Since we are "bonded" in the SWBD at the Neutral don't we let this strap in the transformer stay in the "disconnected" position?