T tonybolin Member Mar 20, 2008 #1 can you help me find the code reference for the required bonding of boxes when installing EMT. When must a box be bonded to the equipment conductor, and when is it not required. thank you
can you help me find the code reference for the required bonding of boxes when installing EMT. When must a box be bonded to the equipment conductor, and when is it not required. thank you
iwire Moderator Staff member Location Massachusetts Mar 20, 2008 #2 Check out 250.148 and Part V of Article 250. Last edited: Mar 20, 2008
raider1 Senior Member Staff member Location Logan, Utah Mar 20, 2008 #3 Welcome to the forum. I agree with what Bob posted, take a look at section 250.148. Chris