mark32
Senior Member
- Location
- Currently in NJ
Hey guys,
I am installing the electric for a spa and have a question about bonding it. This outdoor spa sits on a concrete slab and the spa butts up against a composite deck, the top of the spa is flush, or is very close to being flush, with the surface of the spa. Prior to the slab being poured, I told the homeowner to contact me before that happens so I could come by and clamp a piece of #8 bare to the rebar. At that point, and even now, I was unsure if I even needed to do that but I wanted it in place just in case. So I check my phone one day and see that the homeowner had sent me a text saying that the pour was taking place, that text was an hour old. By time I called him the pour was done. During this, the HO had run out to Lowes and bought some #6 green stranded, so that's what the concrete guy clamped to the rebar. So here are my questions, (1) Do I need a perimeter bond here?
(2) If so, do I connect the #6 to said bond, and if so, does it need to be an irreversible connection?
(3) Considering the top of the spa and the deck are flush, should I strap the bond underneath the walking surface of the deck itself (Within 18-24" of the spa's edge)?
(4) Do you think the inspector will object to the #6 stranded emerging from the slab?
Thanks ~
I am installing the electric for a spa and have a question about bonding it. This outdoor spa sits on a concrete slab and the spa butts up against a composite deck, the top of the spa is flush, or is very close to being flush, with the surface of the spa. Prior to the slab being poured, I told the homeowner to contact me before that happens so I could come by and clamp a piece of #8 bare to the rebar. At that point, and even now, I was unsure if I even needed to do that but I wanted it in place just in case. So I check my phone one day and see that the homeowner had sent me a text saying that the pour was taking place, that text was an hour old. By time I called him the pour was done. During this, the HO had run out to Lowes and bought some #6 green stranded, so that's what the concrete guy clamped to the rebar. So here are my questions, (1) Do I need a perimeter bond here?
(2) If so, do I connect the #6 to said bond, and if so, does it need to be an irreversible connection?
(3) Considering the top of the spa and the deck are flush, should I strap the bond underneath the walking surface of the deck itself (Within 18-24" of the spa's edge)?
(4) Do you think the inspector will object to the #6 stranded emerging from the slab?
Thanks ~