tcoogler
New member
- Location
- Rio Rancho New Mexico
My question is this: Our project has several U/G raceways that are Schedule 40 PVC, with GRC factory 90's at all stub up's. These GRC 90's are required per the project specification. Today, I was told by the Electrical Superintendent that is was an NEC code requirement to have GRC raceways installed vertically from the GRC 90, up through the slab...He said it was a grounding issue. I can find no requirement in the Code (BTW, this projet is under the 2008 NEC. I've looked in both the 2008 and 2011 Code, but to no avail.) that specifically addresses this issue. Is the GRC riser from the GRC 90 required by the NEC? Any help or clarification would be greatly appreciated.
Finally, I have seen this requirement in the Army Corps. of Engineer specifications on previous projects. My thought is that maybe our Electrical Superintendent is confused about what is a specification requirement and what is a Code requirement. Thoughts?
Thank you,
TCoogler
Finally, I have seen this requirement in the Army Corps. of Engineer specifications on previous projects. My thought is that maybe our Electrical Superintendent is confused about what is a specification requirement and what is a Code requirement. Thoughts?
Thank you,
TCoogler