scwirenut
Senior Member
- Location
- Sumter, South Carolina
i am installing a trough over a sub panel 277/480 . 2"emt in pinched holes . im using this for aesthetic purpose of hiding multiple conduits below dropped ceiling. conductors pass through without splices. Do I need any additional bonding?, such as a ground bar. or is that only if their are splices, such as in a j box.