Hi, I'm an apprentice and I ran into something at work and had a Querstion. I asked a few guys at work, looked threw my code book and couldn't find a definitive answer. Any help or clarification would be greatly appreciated.
We were at work opening up panals and transformers. Some of them were 480V, and some 208V. The transformers were 30KVA and 75KVA.
For example, one set up they had was a 480/277V panel feeding a transformer. Then dropping the Voltage down to 208/120V feeding another panal.
There didn't seem to be any consistancy in which they used bonding bushings. A guy I worked with said for 120/208 in which you punch your own hole you didn't need the bushing. But for over 300V you needed a bonding bushing no matter what?
My Question is when do you use bonding bushings?
When can you get away with just the bonding locknut?
Does the Voltage, Concentric KO's, Line or Load matter?
Both sides of the flex(Panal and Transformer)?
Thanks
We were at work opening up panals and transformers. Some of them were 480V, and some 208V. The transformers were 30KVA and 75KVA.
For example, one set up they had was a 480/277V panel feeding a transformer. Then dropping the Voltage down to 208/120V feeding another panal.
There didn't seem to be any consistancy in which they used bonding bushings. A guy I worked with said for 120/208 in which you punch your own hole you didn't need the bushing. But for over 300V you needed a bonding bushing no matter what?
My Question is when do you use bonding bushings?
When can you get away with just the bonding locknut?
Does the Voltage, Concentric KO's, Line or Load matter?
Both sides of the flex(Panal and Transformer)?
Thanks