Hello fellow electricians
I just had a generator room fail an inspection for the following reason, I have PVC conduit coming from the slab, I transitioned over to rigid the to seal tite into the generator, the seal tite was less than 6 feet long, the inspector said I have to have an external bond. Why and what artical states this. I also have a ground wire ran with the feeders in the seal tite
I just had a generator room fail an inspection for the following reason, I have PVC conduit coming from the slab, I transitioned over to rigid the to seal tite into the generator, the seal tite was less than 6 feet long, the inspector said I have to have an external bond. Why and what artical states this. I also have a ground wire ran with the feeders in the seal tite