How are conduits/feeders fed/run to bottom fed switchgear? THrought the slab? Not sure how you would gain entry? Thanks.
It helps if the precise location of the gear, and the exact model to be installed, can be identified before the slab is poured. Then you can lay out the conduit from the outside of the building to the location of the gear, and pour the concrete afterwards.
The phrase "bottom fed" only refers to the power source to the gear. Outgoing conduits can leave via the bottom, if you can plan their routing before you pour the concrete. Otherwise, the outgoing feeders will leave via the top of the gear, and that does not alter the fact that the gear was "bottom fed."
We often use terms like Bottom Fed and Bottom Exit, because they are often not the same.So when you say "refers to power source" you mean the what is feeding the gear. What the gear is feeding....bottom fed doen not apply to??