Given a continuous load of 42A and a noncontinuous load de 60A, the calculation to estimate the OCPD gives 113A (1.25 x 42 + 60). Since this value is close to 110A, is it allowed to use a 110A OCPD, which is very near to the calculated value, instead of a 125A OCPD which is the nearest higher standard?
Thanks