• We will be performing upgrades on the forums and server over the weekend. The forums may be unavailable multiple times for up to an hour each. Thank you for your patience and understanding as we work to make the forums even better.

Bridge Bonding

Status
Not open for further replies.

dmott

Member
I work for a Civil Engineering firm in Ohio and we are the CM on a bridge under construction. The bridge uses steel beams and is located under a 138 kV transmission line, crossing it at roughly a 45 degree angle. The beams sit on an elastomeric bushing, isolating them somewhat from the bridge piers, which are steel reinforced concrete.

Question: Is there any Code requirement or is there an engineering good practice that would require the bridge steel to be bonded and grounded due to the veritcal proximity (~35 feet I am told) to the high voltage transmission lines?

Thanks to anyone who can help.
 

dereckbc

Moderator
Staff member
Location
Plano, TX
Re: Bridge Bonding

This is outside the scope of the NEC. I suspect that a bridge is going to be firmly anchored by concrete peers, which will have abundant re-enforcing steel embedded in the concrete footings. I would look into a Ufer ground system that uses the concrete peers as a ground electrode and specifying the bridge steel members bonded to the concrete re-enforcement rebar.
 

tom baker

First Chief Moderator & NEC Expert
Staff member
Location
Bremerton, Washington
Occupation
Master Electrician
Re: Bridge Bonding

I have heard of an application of traffic signal poles and mast arms under a 112 KV line where the traffic signal poles developed a static charge. The solution was a grounding grid or a ufer ground. The bridge could be "likely to become energized" but thats a stretch. The answer to your question may be more in the NESC as it is a power transmission line issue.
 

bennie

Esteemed Member
Re: Bridge Bonding

Tom: Put a CT on the leg of an iron maiden and read the current flow. Spooky!
 
Status
Not open for further replies.
Top