Grouch1980
Senior Member
- Location
- New York, NY
Hi all,
We have an existing building that will feed a new building about 300 feet away from it. Both buildings are on the same lot, management, owner, etc. Based on NEC article 225, this would be allowed. I'm looking at having the feeder between the buildings trenched 24" below grade. However, the owner wants to save money and have the feeder routed overhead instead of trenched. it's 3 sets of PVC conduit. would the NEC code allow this? can the feeder be routed overhead? and how would 3 sets of conduits even be supported?
Thanks!
We have an existing building that will feed a new building about 300 feet away from it. Both buildings are on the same lot, management, owner, etc. Based on NEC article 225, this would be allowed. I'm looking at having the feeder between the buildings trenched 24" below grade. However, the owner wants to save money and have the feeder routed overhead instead of trenched. it's 3 sets of PVC conduit. would the NEC code allow this? can the feeder be routed overhead? and how would 3 sets of conduits even be supported?
Thanks!