publicgood
Senior Member
- Location
- WI, USA
In an industrial complex under single management, the main service (metal enclosed fused switchgear, 12.47kV) is about 500 feet away from the building complex. If a new feeder is brought to one of the existing buildings for a new test stand, does it require another disconnecting means right before or after it enters the building? Or is the feeder bay outside adequate. The site has a campus switching procedure.
225.32 seems to note (by exception), the campus switching procedure is sufficient. I'm wondering about 225.52 though... it uses the term readily accessible - does 500 feet away meet the requirement?
225.32 seems to note (by exception), the campus switching procedure is sufficient. I'm wondering about 225.52 though... it uses the term readily accessible - does 500 feet away meet the requirement?