If my service disconnect (with GES at disconnect), is remote with from the building and a feeder is supplying the building.
I would need to install a GEC at panel in the building? Correct?

If the service disconnect with OCPD is on the building then I'm done. (With GES at
disconnect)

Is there a point or distance when then remote disconnect and GEC are all that's needed? Regarding if the a GEC has to be also installed at the panel, Is my answer the disconnect has to be within site of building/structure and GEC at the disconnect is all that's required.
 