I'm in a project where the bus duct system was designed to be terminated at the LV switch-gear, the fabrication details show the bus duct routing crossing above the whole unit substation includes switch-gear as well as the transformer and the RMU while maintains only 400mm clearance from BOD to the units, is there any code issue for that installation?