Ken Forest
Member
- Location
- Knoxville
- Occupation
- electrician
we are reviewing a subcontract offer of 6 MW, MV system. The design they propose uses CAB Hanger, above ground DC and AC wiring to MV transformer skids.
we met a field supervisor, saying he hates the CAB Hanger. I am trying to find some pros and cons to decide what's the best. if we can avoid tons of trench work in the wet cold days, to me, it's a win. can somebody explain what are the cons using this?
Thanks
we met a field supervisor, saying he hates the CAB Hanger. I am trying to find some pros and cons to decide what's the best. if we can avoid tons of trench work in the wet cold days, to me, it's a win. can somebody explain what are the cons using this?
Thanks