I've just heard of cable limiters recently. I'm wondering if they can be used to reduce incident energy on the line side of our service disconnect. In ETAP I'm able to use them to drastically reduce the incident energy. In this application, with 4 conductors per phase, if I lose a conductor due to the cable limiter blowing the remainder of the conductors will now carry the full load for that phase. Is there a way to detect or monitor for this condition? Anyone familiar with using them to reduce incident energy?