sdenslow
Member
- Location
- Ormond Beach Fl
We cut a shallow groove in a concrete slab to add a floor outlet. We used rigid non metalic conduit. The AHJ failed the inspection quoting Table 300.5 Minimum cover requirements. He said I must have 2" of concrete cover over my conduit. I said 300.4.F Exception 1 says I can install my conduit without 2" of concrete cover. Who is correct?