mstrlucky74
Senior Member
- Location
- NJ
have job were all they give is the motor symbol on the E drawing with the horeepower within the symbol. some of the motors show on the panel schedule. some questions. need guidance on sizing. FYI this is only budgetary for us.
1. for the motors that show on panel schedule they only show the breaker size and the kw[or maybe kva..cant remember] for the motors. so in this instance if i wanted to size the wire would i go off the motor hp,breaker size or kw/kva?
2. so i guess i need to know the answer to #1 for this question. when sizing a motor based on HP i believe i need to use the FLA based on NEC??
3. what is the NEC rule for when a disconnect/OCPD is needed next to the motor?
thanks a lot for the help on this.
Sent from my SM-G955U using Tapatalk
1. for the motors that show on panel schedule they only show the breaker size and the kw[or maybe kva..cant remember] for the motors. so in this instance if i wanted to size the wire would i go off the motor hp,breaker size or kw/kva?
2. so i guess i need to know the answer to #1 for this question. when sizing a motor based on HP i believe i need to use the FLA based on NEC??
3. what is the NEC rule for when a disconnect/OCPD is needed next to the motor?
thanks a lot for the help on this.
Sent from my SM-G955U using Tapatalk