Coastalguy1
Member
- Location
- Virginia Beach, VA
I thought I had this but sometimes you question things-
Example-
208v 1phase equipment- (counter top electric oven) 35.4A total
To calculate and show on a panel schedule which is correct?
#1- 35.4A/2= 17.7A per phase
#2- 35.4A x 1.732/2= 30.65A per phase
Thanks in advance for providing some clarity.
Example-
208v 1phase equipment- (counter top electric oven) 35.4A total
To calculate and show on a panel schedule which is correct?
#1- 35.4A/2= 17.7A per phase
#2- 35.4A x 1.732/2= 30.65A per phase
Thanks in advance for providing some clarity.