I recently came across a situation where there were several large cables (42 500MCM cables) being run in a single cable tray. Just prior to installation there became a concern over the amount of cable weight in the tray (aprox 78lbs/ft) and how to best support the cable tray for the total amount of weight.
The design for this project specified the size and quantify of the feeders to be routed overhead and left the actual routing of the feeders up to the contractor.
In a situation such as this who's responsibility would it be for determining how to properly support the cable stray for the given weight? Would it be the responsibility of the contractor to either provide adequate support or break it up into multiple cable trays, or is the engineer responsible for providing a support detail that will adequately support the cable weight?
I would think that this would fall under the responsibility of the contractor, if the engineer only specified cable size/quantity and left the routing up to the contractor? Perhaps maybe if the engineer specified the number of trays and the exact routing of those trays then he would be responsible for a details but otherwise it would seem to fall on the contractor?
There was a concern with hanging tray from the ceiling (roof joists) so it will likely be supported along building columns.
The design for this project specified the size and quantify of the feeders to be routed overhead and left the actual routing of the feeders up to the contractor.
In a situation such as this who's responsibility would it be for determining how to properly support the cable stray for the given weight? Would it be the responsibility of the contractor to either provide adequate support or break it up into multiple cable trays, or is the engineer responsible for providing a support detail that will adequately support the cable weight?
I would think that this would fall under the responsibility of the contractor, if the engineer only specified cable size/quantity and left the routing up to the contractor? Perhaps maybe if the engineer specified the number of trays and the exact routing of those trays then he would be responsible for a details but otherwise it would seem to fall on the contractor?
There was a concern with hanging tray from the ceiling (roof joists) so it will likely be supported along building columns.