SKalkbrenner
Member
- Location
- USA
- Occupation
- Self-Employed
Good afternoon everyone.
I am trying to verify my kWh usage due to several months of unexpectedly high bills!! OUCH!
I have recently (2 months) moved into a converted commercial property which started with a 100A standard service and a 100A 3 phase service. New sub-panels were added for both services, with the 3-phase sub consisting of 2 pole breakers for 240V appliances (only using 2 of 3 legs).
My question(s) involves testing the lines as they enter the building. My understanding is that if my dryer was on a 2-pole breaker, standard service panel - I would use my clamp meter on either hot wire to measure current. I would then multiply by 240 to get w and convert to kW ... If that is correct, could I not also back up and take a clamp reading of each 120V service lines and perform the same calculation (120V x I) to calculate what the standard feed is using?
Again, and I know I have a lot of "ifs" above, if the above calculations are legit, what adjustments do I need to make on my 3 3-phase feeds to make the same calculations? My dryer is currently fed from a 2-pole breaker in my 3-phase sub-panel. Am I taking a significant hit because of this vs. being in a standard panel?
My plan is to measure/calculate at each service feed and then also dive deeper into each circuit as needed.
So - let me have it. Is my plan upside down? Crazy talk? or doable?
Thanks in advance for any/all insight provided.
Steve
I am trying to verify my kWh usage due to several months of unexpectedly high bills!! OUCH!
I have recently (2 months) moved into a converted commercial property which started with a 100A standard service and a 100A 3 phase service. New sub-panels were added for both services, with the 3-phase sub consisting of 2 pole breakers for 240V appliances (only using 2 of 3 legs).
My question(s) involves testing the lines as they enter the building. My understanding is that if my dryer was on a 2-pole breaker, standard service panel - I would use my clamp meter on either hot wire to measure current. I would then multiply by 240 to get w and convert to kW ... If that is correct, could I not also back up and take a clamp reading of each 120V service lines and perform the same calculation (120V x I) to calculate what the standard feed is using?
Again, and I know I have a lot of "ifs" above, if the above calculations are legit, what adjustments do I need to make on my 3 3-phase feeds to make the same calculations? My dryer is currently fed from a 2-pole breaker in my 3-phase sub-panel. Am I taking a significant hit because of this vs. being in a standard panel?
My plan is to measure/calculate at each service feed and then also dive deeper into each circuit as needed.
So - let me have it. Is my plan upside down? Crazy talk? or doable?
Thanks in advance for any/all insight provided.
Steve