I am working in a huge warehouse and i have to quote some major work. They are looking to add 90 retractable cord reels that will be drawing an average somewhere from 7 to 17 amps a peice. No more than 60 reels will be in operation at one time.
While I was on the site visit I recommended adding a subpanel to accomadate the new wiring. I was told there was an abandoned 3phase 100 amp (3 wire with ground B/O/Y) wiring near the desired location. Do u think that this will be sufficeint for this application. Please help