Hi There
I would need some help to size a CB for a Supanel.
What I understand is that if you have a MLO Panel Box rated 125 A you should
hook it up with a 125A feeder from a 125 A CB at the panel which feed the first one.
A question arise to me and it is if I just need to load the 125 A panel with 60A (Connected load), which would be the feeder and the CB from the first panel.
I am discussing that with other people and my opinion is that you should size (despite have a connected load of 60A ) with 125 A feeder and 125 amp CB.
Is that correct or Am I wrong ?
Thank you very much for some help.
I would need some help to size a CB for a Supanel.
What I understand is that if you have a MLO Panel Box rated 125 A you should
hook it up with a 125A feeder from a 125 A CB at the panel which feed the first one.
A question arise to me and it is if I just need to load the 125 A panel with 60A (Connected load), which would be the feeder and the CB from the first panel.
I am discussing that with other people and my opinion is that you should size (despite have a connected load of 60A ) with 125 A feeder and 125 amp CB.
Is that correct or Am I wrong ?
Thank you very much for some help.