brantmacga
Señor Member
- Location
- Georgia
- Occupation
- Former Child
See 2017 NEC 250.62(D)
We are building an addition to our office. Currently, there is a trough with two disconnects feeding two 200A panels, and the GEC’s currently meet the requirements of 250.62(D)(1)(3), in that there is a copper bus bar where the existing CEE, ground rods, and building steel are terminated.
We left additional conduit in the ground from the trough for planned expansion, but it’s just a 3” PVC for the feeder.
I bonded the rebar on the new footer and left stubbed up where the panel for the addition will go.
Is it acceptable to land the new GEC on the ground bar of the new panel and then bond the new disconnect to the grounding bus bar, or do I have to run the new GEC for the CEE and steel directly to the bus bar?
250.62(D) says it must meet the requirements of (1), (2), OR (3), so I’m reading that as it must be one or the other but not a combination of. (1) says it must extend to the disconnect, and then to the common electrode, so I feel like it may be ok to land the new GEC’s in the panel first; I’m having trouble wrapping my head around the language.
Sent from my iPhone using Tapatalk
We are building an addition to our office. Currently, there is a trough with two disconnects feeding two 200A panels, and the GEC’s currently meet the requirements of 250.62(D)(1)(3), in that there is a copper bus bar where the existing CEE, ground rods, and building steel are terminated.
We left additional conduit in the ground from the trough for planned expansion, but it’s just a 3” PVC for the feeder.
I bonded the rebar on the new footer and left stubbed up where the panel for the addition will go.
Is it acceptable to land the new GEC on the ground bar of the new panel and then bond the new disconnect to the grounding bus bar, or do I have to run the new GEC for the CEE and steel directly to the bus bar?
250.62(D) says it must meet the requirements of (1), (2), OR (3), so I’m reading that as it must be one or the other but not a combination of. (1) says it must extend to the disconnect, and then to the common electrode, so I feel like it may be ok to land the new GEC’s in the panel first; I’m having trouble wrapping my head around the language.
Sent from my iPhone using Tapatalk