Suppose you're wiring a newly-built house, and the person in charge (owner, builder, GC, owner's wife, etc.) wants to make a change to something, namely moving a switch/outlet to a different location. Would you typically charge a fee for this? What about if the wiring had not yet been run or the affected boxes hadn't been installed yet? I probably wouldn't charge anything as long as I didn't have to redo anything that I had already done. But I would get annoyed if they asked me to move something after the fact, so I would charge $100 or so (sort of a 'Now-you-tell-me') clause.