Jon C.
Member
- Location
- Escondido, CA
Hi,
I came across this job today. The previous electrician added a single phase manual transfer switch to a existing commercial 3 phase main service. They removed the high leg off the main disconnect, on the load side and ran the two legs and neutral to a 2 pole transfer switch. Now that the building is being remodeled, they are wanting to get new equipment, but the 3 phase has been disabled. They have a single phase 60 kva trailer mounted genset, so are reluctant to buy a new 3 phase generator.
I mentioned that there choices were to restore the 3 phase panel by adding the missing wire, if they want to use the single phase generator, install a new stand-by panel and run all the single phase loads into this panel and hook that up through the transfer switch.
I see this as a code violation, yet they claim the work was done by a licenced electrical contractor and inspected...
Any thoughts?
Thanks,
Jon
I came across this job today. The previous electrician added a single phase manual transfer switch to a existing commercial 3 phase main service. They removed the high leg off the main disconnect, on the load side and ran the two legs and neutral to a 2 pole transfer switch. Now that the building is being remodeled, they are wanting to get new equipment, but the 3 phase has been disabled. They have a single phase 60 kva trailer mounted genset, so are reluctant to buy a new 3 phase generator.
I mentioned that there choices were to restore the 3 phase panel by adding the missing wire, if they want to use the single phase generator, install a new stand-by panel and run all the single phase loads into this panel and hook that up through the transfer switch.
I see this as a code violation, yet they claim the work was done by a licenced electrical contractor and inspected...
Any thoughts?
Thanks,
Jon