I was confronted with the question of whether or not conduit runs could change size in the middle of the run. for example 1" PVC/GRC stubbs up from below ground and at approx 12" AFF a coupling is installed on the GRC threads then an 3/4 emt connector and 3/4 emt piping is continued from that point to a destination point. It looks like 300.10 or 300.12 would prohibit this from happening but not sure?