Re: CHECKING RESISTANCE
Chip out enough finish material to get access to the rebar. Use a continuity indicator to confirm a bond. Use long wires for test leads.
Get the inspector to supply definite point to point testing requirements.
Does the inspector plan to witness the test? If not, take photographs of the results and procedure used.