Hi,

I'm currently working on a project that deals with Class 1 Div. 2. The gas is methane. I am running new conduits and conductors from an existing MCC to an undergound pullbox (precast H20 Loading), and from the pullbox to a control panel on the Sludge Skid. I have provided seal offs at the entrance to the control panel. But I can't provide seal offs from the pullbox to the MCC because it is underground conduits. Does anyone know how i can resolve this issue?
 