drbond24
Senior Member
- Location
- Barboursville, West Virginia
I have a situation where a customer wants to install gas cylinders in a room already containing a panelboard, wire in conduit, etc. Does this mean I must replace all the electrical equipment in the room with Class 1, Division 2 equipment? Also, what if the cylinders were outside the room and only the piping went through the space with the panelboard.
It seems to me that either way, the space is Class 1 Div 2 and I need to replace the panelboard with one in a NEMA 7 enclosure and replace all conduit with threaded rigid steel.
I would just like a second opinion.
It seems to me that either way, the space is Class 1 Div 2 and I need to replace the panelboard with one in a NEMA 7 enclosure and replace all conduit with threaded rigid steel.
I would just like a second opinion.