I have a 100 amp service #2 AWG with a 200 amp fused disconnect before the meters (3). Off of this disconnect an 11/4 pipe travels 100' thru 2 buildings to hit 2 of the meter sockets feeding 100 amp panels, both of these have nonfused disconnects after there meter.
In this 11/4 pipe we have 3 #3 AWG feeding these services. Nothing is grounded on any of the panels. My question is are you allowed to hit a fused disconnect before the meters or do you need a tap box then feed your meters ,fused disconnect, panels?