I'm looking for constructive criticism on the following, and if you think it is merited, support in the form of comments from you on 5-6__5-46. Thanks, Jim Williams
4 Comment:
100 Definitions.
Effective Ground-Fault Current Path. An intentionally constructed, low-impedance electrically conductive path designed and intended to carry current under ground-fault conditions from the point of a ground fault on a wiring system to the electrical supply source and that facilitates the operation of the overcurrent protective device or ground-fault detectors. [ROP 5?6]
250.2 Definitions.
Effective Ground-Fault Current Path. An intentionally constructed, low-impedance electrically conductive path designed and intended to carry current under ground-fault conditions from the point of a ground fault on a wiring system to the electrical supply source and that facilitates the operation of the overcurrent protective device or ground-fault detectors. [ROP 5?46] [ROP 5?13, ROP 5?14]
5 Statement of Problem and Substantiation.
In 100 insert a space between under and ground-fault.
In 250 delete the definition. 100 definitions apply to 250. Duplicating the definition ? word-for-word ? serves no purpose.
4 Comment:
100 Definitions.
Effective Ground-Fault Current Path. An intentionally constructed, low-impedance electrically conductive path designed and intended to carry current under ground-fault conditions from the point of a ground fault on a wiring system to the electrical supply source and that facilitates the operation of the overcurrent protective device or ground-fault detectors. [ROP 5?6]
250.2 Definitions.
Effective Ground-Fault Current Path. An intentionally constructed, low-impedance electrically conductive path designed and intended to carry current under ground-fault conditions from the point of a ground fault on a wiring system to the electrical supply source and that facilitates the operation of the overcurrent protective device or ground-fault detectors. [ROP 5?46] [ROP 5?13, ROP 5?14]
5 Statement of Problem and Substantiation.
In 100 insert a space between under and ground-fault.
In 250 delete the definition. 100 definitions apply to 250. Duplicating the definition ? word-for-word ? serves no purpose.