COMMERCIAL LOAD CALCULATION FOR NYC

Status
Not open for further replies.
Question #1
Small office in NYC, the existing space has a single phase panel. The new load calculation I came up with is 61,235VA

The service is 120v/208v single phase. Do I do the 61,235va(208V x 1.73) even though I only have 2 hot phases and no 3 phase in the panel.
Or do I just do the 61,235va / 208v = 294 AMPS

Question #2
Also if I have (50) 20A receptacles @ 180VA do I also need to count the circuit quantities that those (50) Rec will be connected too?
 

topgone

Senior Member
Question #1
Small office in NYC, the existing space has a single phase panel. The new load calculation I came up with is 61,235VA

The service is 120v/208v single phase. Do I do the 61,235va(208V x 1.73) even though I only have 2 hot phases and no 3 phase in the panel.
Or do I just do the 61,235va / 208v = 294 AMPS

Question #2
Also if I have (50) 20A receptacles @ 180VA do I also need to count the circuit quantities that those (50) Rec will be connected too?

Ans 1: Correct, 294 AMPS
Ans 2: 50 x 180VA =9,000 VA
 
For answer 2, I know that (50) rec X 180 VA = 9,000VA but what I was asking was; these (50) rec will be fed with (10) 20 amp circuits. Looking at my Mime Holt book it looks like the following? ":

9,000 VA for the rec

then

120v X 20A X (10) circuits = 24,000VA

24kva + 9kva = 33,000va
 

jglavin427

Member
Location
Denver, CO
Let's assume the (10) 20A circuits each feed 5 recepts. The load on each would then be 900 VA, for a total load on the 10 circuits of 9000 VA. In other words, you do not need to add an additional 20A per circuit on top of the connected load.
 
Status
Not open for further replies.
Top