Hello Guys and Gals.
One of our departments recently moved to a multifloor building that have other tenants on the upper floors not associated with us. They had their own phone sytem installed by our communications dept. He said he needed wire connected to building ground. I assumed he meant grounding electrode system.
I installed a 10awg stranded wire to nearest building steel with a listed device.
Is there anything wrong with this installation per NEC or anyother code that may govern this? I my opinion, 800.100B(2)2 allows this.
What is meant by intersystem bonding termination per 800.100B(2)
Thanks for replies.
One of our departments recently moved to a multifloor building that have other tenants on the upper floors not associated with us. They had their own phone sytem installed by our communications dept. He said he needed wire connected to building ground. I assumed he meant grounding electrode system.
I installed a 10awg stranded wire to nearest building steel with a listed device.
Is there anything wrong with this installation per NEC or anyother code that may govern this? I my opinion, 800.100B(2)2 allows this.
What is meant by intersystem bonding termination per 800.100B(2)
Thanks for replies.