I have a discussion we a collegue regarding Con Ed Ruling-The school service is 120/208,3 phase 4#500Kcmil,. The additional load to be added to the school was approximately (228kw/750amps).
Con ed ruling came that service reinforcement was needed and that con ed was to install 2-4" conduit and one set of 500kcmil service cable- my collegue think that this is wrong- that if come ed installed two sets of 5ookcmil, the customer will tap with max 2 sets of 500kcmil.-- I think that it is right. my interpretation of the ruling and con ed dwg. no. Eo-6208-c rev. 16 is that con ed will come in with one extra set of cables (remenber there is already one set), but the customer will tap to these cable with 3 sets of 500kcmil- i'm thinking that con ed will provide 2 new 4" conduit in additon to the existing one-
I have called the rep assigned to this project, but I have not heard from him.
thanks
Con ed ruling came that service reinforcement was needed and that con ed was to install 2-4" conduit and one set of 500kcmil service cable- my collegue think that this is wrong- that if come ed installed two sets of 5ookcmil, the customer will tap with max 2 sets of 500kcmil.-- I think that it is right. my interpretation of the ruling and con ed dwg. no. Eo-6208-c rev. 16 is that con ed will come in with one extra set of cables (remenber there is already one set), but the customer will tap to these cable with 3 sets of 500kcmil- i'm thinking that con ed will provide 2 new 4" conduit in additon to the existing one-
I have called the rep assigned to this project, but I have not heard from him.
thanks