hmspe
Senior Member
- Location
- Temple, TX
- Occupation
- PE
I have a contractor asking for approval to pour a separate "footing" to add a CEE on a project under construction. 2005 NEC. This is a 4 unit condo project which passed the "Footing/Ufer" city inspection, so provisions for a CEE must have been made in the building's footing. The builder installed two ground rods instead, which I have declined to approve. The City Inspector has asked for a letter from the PE (that's me) approving adding a new trench and "footing" in place of chipping into the existing footing. I can't/won't personally approve chipping out the existing footing, and apparently there is some issue with getting the Structural Engineer's approval. The building is well into drywall phase.
I don't particularly like the separate/unused footing idea, mostly because there will be no weight of the building on it, but thought I'd ask here for input. If this works well and/or is generally accepted, or if you have other comments I'd like to hear them.
Thanks,
Martin
I don't particularly like the separate/unused footing idea, mostly because there will be no weight of the building on it, but thought I'd ask here for input. If this works well and/or is generally accepted, or if you have other comments I'd like to hear them.
Thanks,
Martin