I have a project where I'm relocating an MCC to another location. The MCC feeder conductors will decrease in length. Conductors feeding loads in the facility will be increased approximately 100 ft. I have a potential voltage drop issue that I'm concerned about. Is it permissible from an NEC standpoint to splice a larger conductor to the existing conductors so long as the smaller conductor is protected at its ampacity by the overcurrent device that is upstream of the first conductor?