Given the following: I'm in a chemical plant where the equipment motors / instruments are exposed the the weather. I have cable tray with tray rated cables running thru out the process, again exposed to the weather. I branch off the cable tray with conduit to a motor (approx. 30 ft). One engineer says I need to install a drain in the conduit and another engineer said I can leave the "tee" open as this will accomplish the same thing as the drain. The engineer that said to use drains cites NEC 501.15. The engineer that said not to use drains, considers the conduit run from the tray to the motor / instrument as part of the tray system and cites NEC 392.6.
Reason behind the debate is we have had problems using drains in this type of application. What say all you NEC guru's?
Reason behind the debate is we have had problems using drains in this type of application. What say all you NEC guru's?