I am designing a system where it involves low voltage and data communication cables would reside in the same conduit. This particular conduit involves underground pvc, but stubs out as a rigid conduit. These are in concrete encased form. From my understanding, the conduit fill rate should not exceed at 40%. I was told that it can be as high as 70%. Which statement is true? An urgent response is greatly appreciated.